Six months, three tracks, four milestones. Month 6 opens no new work.

A nine-month project fails in one of two ways: because everything is built until the last day and then tested in a few, or because the scope keeps moving during stabilisation. This plan rules out both.

Delivery plan — 6 months

M+9 · go-live

M1
M2
M3
M4
M5
M6
Framing · scope signed
Ledger · immutable entries
Commission engine
Unified partner module
Intake · three-way reconciliation
Bank reconciliation · statements
Design system · core screens
Counter · tills · offline mode
Virtual vault · liquidity forecast
Partner operations · exceptions
Reporting · dashboard
Infra · 2FA · roles · multi-tenant · chained audit
Client file · KYC documents
Screening · thresholds · security audit · load
Timed restore drill
No new work — UAT, training, cutover
Ledger & connectors — Adama
Business modules & UI — Fatima
Platform, security & compliance — Massar
Whole team

What shapes the calendar

Every month ends with a delivery. A working version is deployed to your staging environment. There is no month without a delivery.

Your staging environment opens at the end of M2, not at month 6. Your teams work on it continuously, on fictitious data, for the whole duration of the project.

Security comes before the end. Tooled audit and configuration review at month 5, with a dated remediation plan — so that fixes have time to be made and re-tested before go-live.

So does load. Performance tests at month 5, at three times the volume communicated at framing.

Requests frozen on the 15th of month 5. No new request is accepted after that date, whatever its outcome.

Month 6 opens no new work. It completes reporting — screens that read off a ledger validated at month 2 — then carries fixes, acceptance testing, training and opening. It is the project's reserve, the only kind of margin that does not dissolve under calendar pressure.

Month by month

MonthDelivered to your staging environmentQuality, security, migrationMilestone
M1Framing, chart of accounts, scope frozen and signed · authentication, 11 roles, multi-branch, multi-tenant isolation, chained auditContinuous integration, automated tests, dependency scanningJ1 Scope signed
M2Ledger: immutable entries, reversals, journals, trial balance · design system and core screensYour staging environment opens—
M3Tills — six types, opening, movements, counting, discrepancies, closing · four-part commissions · counter and offline modeEnd-to-end tests on the branch dayJ2 A full branch day
M4Unified operations module · first partner configuration · CRM and KYC · multi-country and multi-currencyAcceptance testing on M2–M3 · migration sample requested—
M5Five partner configurations · five-channel intake · three-way reconciliation and exception queue · RBTAcceptance testing on M4 · data anomaly report deliveredJ3 A statement imported and reconciled
M6Compliance: screening, thresholds, structuring, risk scoring, case files, filings · general administrationTooled security audit · dated remediation planJ4 An alert raised and documented
M7FX · bill payment · top-up and Mobile Money · full accounting · Visa cards and banking partnersPerformance tests · acceptance testing on M5–M6J5 Financial services on staging
M8Reporting and BI · documents and OCR · API and webhooks · decision assistant — freeze on the 15thExternal penetration test · load testing · dry-run data migrationJ6 Multi-branch steering
M9No new functionality. Fixing reservations, finishing touches, documentationFormal acceptance testing · penetration re-test · timed restore · pilot branch then wavesJ7 Go-live

The milestones that release a payment

Three of the four milestones release an instalment, alongside the one paid on signature: J1 at month 2, J2 at month 4, then go-live at month 6. A milestone is not a date — it is a list of numbered criteria, run in your presence, on your environment, with your test data.

What makes this calendar achievable

Six partner modules reduced to one configured module. The operation, commission and posting logic is written and tested once instead of six times.

Scope frozen and signed at framing. This removes the main cause of drift: the continuous redefinition of expected depth.

Configuration rather than development. Rate cards, thresholds, charts of accounts, labels and roles are data entered by your administrators.

The counterpart. A team of three can absorb neither scope drift nor decision delays. The scope freeze and the single point of contact within 48 hours are not boilerplate: without them, the nine-month commitment does not hold.

Beyond V1

Strategic horizon

V1

Version 1

Month 6

Operations, tills and treasury, ledger and accounting, compliance, reconciliation, reporting · multi-branch, multi-currency, multi-tenant

Our scope
V2

Stabilisation

Months 7–12

Maintenance and support included · timed restore drill at month 12

Included
V3

Developments

Beyond

Financial services, additional connectors, advanced steering, Visa cards, decision assistant · six phases quoted at firm prices

Firm prices, valid 18 months

V1's module boundaries and payment ledger are designed today to host V2/V3 without a rebuild (CDC §2).